Craftsman on the Park, Phase 2
Construction in progress for a second addition to match an earlier Craftsman Style makeover. Take a look at the first addition on Houzz. See the first transformation on our web site.
Project Team: Lawrence and Gómez Architects
Builder: Jeff Becker Construction
Structural engineering: Gebau Engineering
Audio and video design: ListenUp
39. Tech and traditional coexist in this new media room. Click to see finished project on Houzz.
38. Two flatscreen TV’s and a projection screen provide adequate media for varied formats.
36. October 2012
35. October 2012
34. Spiral stair detail
33. Spiral stair
32. Deck rail progress

Theo Merrin and Eric Decaria start with the newel posts and then add the horizontal members of the composite deck rail.
31. New driveway poured and curing
30. Finish on trusses
29. Truss detail
28. Driveway prep
27. Click to view these carpenters setting cabinets on YouTube.
26. Interior wood trusses ready to receive stain
25. Bottom chord of a truss

The bottom chord of a truss has been carefully shaped and is ready to be fastened to the other truss members. A channel cut into the top will hold an LED strip that will illuminate the ceiling for soft ambient lighting.
24. Painter

A painter with Town and Country Painting masks glass and walls, leaving the wood trim exposed to receive stain.
23. Exterior bracket and trim

Exterior bracket detail, window trim, soffits, fascia, and shingles installed and ready to receive paint and stain.
22. Exterior trim carpenter
21. Siding and Exterior Trim

Scaffold in place, siding and exterior trim in progress. Because this house sits in a 100-year flood plain, the bottom courses of gray siding are water-resistant cement board. The wood siding matches the existing house. Also notice the flood vent cut into the wall.
20. Decorative Template
19. Deck Framing
18. Deck Framing
17. Pier Cap
16. Deck Beam
15. Insulation
14. August 2012
13. August 2012
12. August 2012
11. August 2012
10. General Contractor in August 2012
9. July 2012 – Framing progress
8. July 2012 – Lead framer
7. July 2012 – Floor joists
6. July 2012 – Mountain Concrete
5. July 2012 – Garage slab
4. June 2012 – New garage foundation
3. May 2012 – Original garage seen from the west.

West elevation (back yard) showing original garage attached to the house. It will be deconstructed and reconstructed to receive a new family room above.
2. Spring 2012 – Original garage seen from the street elevation
1. Spring 2012 – Drawing of east elevation, below, showing new garage and family room addition
Pingback: Raw Hide and Cosmos | lawrence and gómez architects
Pingback: Raw Hide and Cosmos and Vista | lawrence and gómez architects