Meadow House under construction
Project Team: Lawrence and Gómez Architects
Gary Rosson, Western Soils; Jon X. Giltner, Structural Eng.
Strong Framing Co., Inlighten Studios, Namaste Solar
________________________________________________________
68. Detail of fireplace stone

At the corners tile setter Erick Muniz carefully toothed in alternating rows of Coppersmine slate in ledge stone pattern.
67. Fireplace cladding
66. Granite installation by Moros Fabrication

Rey Flores and the crew of Moros Fabrication installs leathered Nordic Black granite counter tops.
65. Interior painting

Painters’ ladders and tools
64. West elevation

West elevation ready for stucco color
63. Rediscovered Woods recycles tree, click for more.

Kevin Kisich brings the sawn tree on site to template the raised counter top. Click photo for more.
62. Namaste Solar lays out panels.

Martin Beggs of Namaste Solar lays out solar array on the roof prior to installation.
61. Gary builds stair rail.

Carpenter Gary Friedlander lays out the rail pieces prior to installation.
60. Wrapped beam

Wrapped beam ready to receive stain and light fixtures
59. Carpenter Matt prepares beam

Carpenter Matt Fitzrandolf installs wood wrap on beam.
58. Carpenter Matt Fitzrandolf inspects wood

Carpenter Matt Fitzrandolf inspects wood.
57. Exterior stone veneer – click here to watch video

Stone veneer on metal lathe by Howard Davis Masonry
56. Boys’ bath floor

Wood texture tiles laid and ready for grout
55. Master bath palette

Tile, pebbles, and paint color for Master Bath
54. Meanwhile, interior finishes continue

Desk by deck entrance in progress
53. August 2012 – Painter

Chad with Dave Barry Painting sprays colored stain on fascia, trim, and soffits.
52. August 2012 – Painters

Painters unmask windows and shingles after color is applied on trim.
51. August 2012 – Exterior painting

Dave Barry’s painters work on long ladders on the west side of the building.
50. August 2012 – Spiral stair by Rob Goehring of Quality Metal Fabricators

Plan view of spiral stair in place
49. August 2012

Scott Reardon, the general contractor, steadies the stairs as Mike and Lou of Quality Metal Fabricators bolt it to the structure.
48. August 2012

Crane lifts spiral stair off the metal fabricator’s trailer.
47. August – Green Flooring Company

Paul of Green Flooring Company walks on the engineered flooring during installation.
46. early August – red birch cabinets from Piper Wycoff of Kitchens by Wedgewood

Cabinet setters’ tools seen in the kitchen.
45. early August

Randy and Rory of Wedgewood install the buffet cabinets.
44. July 2012 – Northwest corner
43. July 2012 – Pondering a difficult detail

Trim carpenter Jack Sasson, general contractor Scott Reardon, and trim supplier Scott Brizol (of Rocky Mountain Forest Products) ponder a difficult detail.
42. July 2012 – Plastic covers windows
41. July 2012 – Electricians at work
40. July 2012 – Drywaller on stilts
39. July 2012 – Drywall scaffolding
38. July 2012 – Insulation

Inside, an installer with Fossil Creek sprays a skim coat of foam insulation under the roof sheathing. Then the cavity was filled with recycled cellulose to achieve a rating of R-53.
37. June 2012 – Garage doors installed

Dave Kilcrease of Reardon Custom Homes ascends the front steps. The newly installed garage doors can be seen in the foreground.
36. June 2012 – Rough-ins continue in ceiling/floor

Rough-ins continue. Carefully coordinated trades fill the joist space between the floor and ceiling with duct lines for air conditioning, orange pipes for fire sprinklers, orange tubing for radiant heat, j-boxes for light fixtures and smoke detectors, red and blue hot and cold water lines, cables for photovoltaics, coaxial cables for media/communications, and electrical wiring.
35. May 2012 – Rough-ins in walls and floors

Meanwhile inside, plumbing, electrical, and air conditioning duct work are roughed in. This is a view of wall in the kitchen.
34. May 2012 – Roofing and front porch
33. April 2012 – Front steps
32. April 2012 – Back deck framing
31.March 2012 – Masons erect block columns. Click here to watch video.
30.Masons prepare block
29. Window set in place
28.Installing flexible flashing
27.Framers set windows in openings
26. March 2012 – Window units arrive on site
25. Opening captures Flatirons
24. Window openings frame snow-capped Front Range
23. March 2012 Roof trusses in place
22. Setting ridge beam – click here to see a YouTube video of this and other framing moments
21.
20.
19.
18.
17. February 2012 Framing
16. February Backfilling
15. February
14. February
13. January 2012 Structural slab

Detail of rigid insulation over void forms over vapor barrier on gravel base. Over this assembly, the plumbers will lay the radiant heat tubing that will be encased in the structural slab.
12. January
11. January Forming and pouring foundation

Formed, poured, and insulated foundation walls will be ready for backfill once the main floor is framed in place
10. December 2011 Caissons – click here for YouTube video
9. December
8. December Surveying
7. November 2011
6. Summer-Fall 2011 Design and engineering

SketchUp three dimensional drawing looking out from the rooftop deck towards the Flatiron mountains of Google Earth.
5. Summer-Fall 2011
4. Summer-Fall 2011
3. Summer-Fall 2011
2. Summer-Fall 2011
1. Summer-Fall 2011
Pingback: Drawings and Design, 3D « Lawrence and Gómez Architects
Pingback: reduce, reuse, RECYCLE « lawrence and gómez architects
Pingback: Fall projects « lawrence and gómez architects